Woodlands Resource Centre, Falkirk Community Hospital
Sector: | Healthcare |
Participant: | NHS Forth Valley |
Location: | Falkirk |
Capital Value: | £1.9M |
Procurement: | NEC3 Option A |
GiFA: | 2,534m² |
Start Date: | November 2014 |
Construction Period: | 23 weeks |
Breeam Target: | N/A |
Key Appointments
Fast track project procured via the East Central hub FM Services Un-scoped Minor Works process. It involved the design and refurbishment of the former Wards 18 & 19 building to form the new Woodlands Mental Health Resource Centre.
Key Appointments
Contractor: | Robertson Construction |
FM Operator: | N/A |
Architect: | Austin-Smith Lord |
Civil & Structural Engineer: | sub consultant to +96Architect |
Building Services: | FES |
CDMC: | Kirk & Marsh |
BREEAM Assessor: | N/A |
hub PM Contact: | Paul Lang |