Angus House – Alterations for Agile Working
Sector: | |
Participant: | Angus Council |
Location: | Forfar |
Capital Value: | £1.4m |
Procurement: | JCT Minor Works |
GiFA: | N/A |
Anticipated Start Date: | 6th June 2016 |
Construction Period: | 63 weeks |
Breeam Target: | N/A |
Project Description
hub East Central Scotland has been engaged by Angus Council to support the Transforming Angus Team to deliver its Agile Working and Estates Review work steams. As part of this process four phases of internal alteration works are planned in Angus House, to maximise the desk capacity and increase the number of staff working out of the building. Alterations include revised layouts to each floor to provide open plan office environment, new break-out and kitchen areas, new lighting and window blinds together with new floor coverings and decoration.
Key Appointments
Contractor: | Robertson Construction Tayside |
FM Operator: | N/A |
Architect: | Angus Council |
Civil & Structural Engineer: | N/A |
Building Services: | TUV-SUD |
Principle Designer: | Angus Council |
BREEAM Assessor: | N/A |
hub Project Manager: | Wayne Sutherland |
Tier 1 Project Manager: | Dave Barber |