Woodlands Resource Centre, Falkirk Community Hospital

Sector: Healthcare
Participant: NHS Forth Valley
Location: Falkirk
Capital Value: £1.9M
Procurement: NEC3 Option A
GiFA: 2,534m²
Start Date: November 2014
Construction Period: 23 weeks
Breeam Target: N/A

 

Key Appointments

Fast track project procured via the East Central hub FM Services Un-scoped Minor Works process. It involved the design and refurbishment of the former Wards 18 & 19 building to form the new Woodlands Mental Health Resource Centre.

 

Key Appointments

Contractor: Robertson Construction
FM Operator: N/A
Architect: Austin-Smith Lord
Civil & Structural Engineer: sub consultant to +96Architect
Building Services: FES
CDMC: Kirk & Marsh
BREEAM Assessor: N/A
hub PM Contact: Paul Lang