Unit 5, Falkirk Community Hospital

Sector: Healthcare
Participant: NHS Forth Valley
Location: Falkirk
Capital Value: £1M
Procurement: NEC3 Option A
GiFA: 477m²
Anticipated Start Date: November 2014
Construction Period: 6 weeks
Breeam Target: N/A

 

Project Description

Fast track project procured via the East Central hub FM Services Un-scoped Minor Works process. It involved the design and refurbishment of an existing Mental Health Day Centre to form the new Unit 5 Inpatient Ward.

Design development and Construction Works were accelerated to meet Employer winter bed requirements with siteworks staring 17 November 2014 for handover on 6 January 2015.

 

Key Appointments

Contractor: Robertson Construction
FM Operator: N/A
Architect: Austin-Smith Lord
Civil & Structural Engineer: sub consultant to Architect
Building Services: FES
CDMC: Kirk & Marsh
BREEAM Assessor: N/A
hub PM Contact: Paul Lang