NHS FV GP Premises Prioritisation

Sector:  
Participant: NHS Forth Valley
Location: 10 No. Locations
Capital Value: £625,000
Procurement: Minor Works
GiFA: 6,569m2
Anticipated Start Date: March 2018
Construction Period: 15 weeks
Breeam Target: N/A

 

Project Description

Internal and external fabric repair/upgrade works to 10Nr GP practices incorporating minimal M&E works at specific branches. This project comprises phase 1 of a 4 year programme coordinated and managed by NHS FV estates department.

Key Appointments

Contractor: Robertson Group
FM Operator: N/A
Architect: N/A
Civil & Structural Engineer: N/A
Building Services: N/A
Principle Designer: N/A
BREEAM Assessor: N/A
hub Project Manager: Jim Allan
Tier 1 Contractor Contact: Peter Chambers